You open the drawings and the project has a window and door schedule. Then you look at the wall sections and elevations, and they tell a different story. The schedule says forty units at 36 by 72. The elevation draws twenty-eight openings, and the section shows a header that cannot fit a 36-inch unit. Which number goes in your takeoff?
The short version: the window and door schedule is the source of truth for what is being sold — the product, the quantity, and the size. The wall section is the source of truth for how it is installed — the rough opening, the header, and the conditions that can veto a scheduled unit. When they disagree, you do not pick one and move on. You resolve the conflict, price the schedule as drawn, and load the risk of the wall section onto the columns that can carry it.

Why the schedule wins on quantity
A window and door schedule is a tabular contract between the architect and everyone downstream. Each line names a type, a size, a frame and glass specification, a hardware group, and — in Florida — often a product approval or design-pressure requirement. It is read column by column, and it is what the submittal, the shop-drawing, and the purchase order all trace back to.
That is why your quantity takeoff runs off the schedule, not off counting elevation marks. An elevation shows every opening on that face, but it does not aggregate. Twenty-eight marks on the north elevation and twelve on the east can still be the same schedule line and the same product type. You mention only the elevation marks at your peril — you are one counting error and one schedule column away from ordering the wrong number of units.
The arithmetic rule: every line in the schedule is a unit of work, and every unit in your takeoff should tie to a schedule line. If you have a unit that maps to no schedule line, or a schedule line with no matching unit, you have found a drafting error. That discovery is the job. It is not a cause to guess.
Where the wall section actually rules
The wall section is not competing with the schedule on count. It competes on condition. A schedule can tell you a 36 by 72 unit goes in a storefront system. It cannot tell you the header is a 6-inch lintel with 2 inches of bearing, or that the masonry opening is a block of solid mullion, or that the opening lands directly under a beam. Those live in the section, and they are what kill an as-drawn unit.
Two conditions that routinely veto a schedule line:
- Rough-opening depth. A section that shows less rough opening than the scheduled frame requires means the frame does not fit without rework — a new header, a structural change, or a smaller unit. That is not a takeoff error you can paper over with an allowance.
- Mullion and supporting conditions. Edge-of-slab, spandrel, and corner conditions in section often force a heavier frame or a different anchor than the schedule’s base product. A compliance-minded reviewer compares anchor type, embedment, and edge distance against the product approval — a mismatch at the anchor is a first-pass bounce.
So the section is not the enemy of the schedule. It is the check that runs before you commit a dollar. Read the schedule for what, and the section for whether it fits.
What to do when they genuinely disagree
You cannot fix the drawing on the bid. What you can do is decide how to carry the conflict:
- Price the schedule as drawn. The schedule is the contract quantity and the approved product. Your base number should reflect it. Adding units or sizes that the schedule does not show, because an elevation looks like it has more openings, is how you hand the owner money you will not be paid for.
- Flag every section conflict to the schedule. For each hashed opening, name the discrepancy — header too shallow, opening too narrow, mullion condition that changes the product. You are creating the paper trail that turns a bid-time guess into a documented RFI when the job is awarded.
- Load the risk onto the right columns. If a section forces a heavier frame or a different anchor, that cost belongs in the schedule line for that type or in a documented contingency — not spread invisibly across the takeoff where the arithmetic stops being defensible. A schedule of values that is defensible to a reviewer is built from a defensible takeoff.
The one number you never invent is the count. You take it from the schedule, adjust only with a written basis, and carry the exceptions separately so the reviewer sees the decision.
The disagreement that is actually a scope gap
Sometimes the schedule and the section do not disagree — the section is simply missing. A unit is scheduled, but no section, elevation detail, or head-and-sill detail shows where it lands. That is not a conflict to resolve. It is a scope gap in the documents themselves, and it is where bids get blown up when the GC’s estimator assumed it and the architect did not.
Treat a missing detail as unverified, not as free. Price the scheduled unit, but keep its installation open in your coverage — the header, the anchor, and the waterproofing are not established until a detail shows them. The same logic that gets a compliance package kicked back when conditions under it are not established applies on the estimating side too.
The takeoff habit that makes this painless
None of this is hard on a clean single-opening project. It compounds when you have dozens of units, several schedules, and suppliers substituting products as the job moves. The habit that keeps it manageable is structural: line every unit to its schedule line, and line every schedule line to its section or detail. When that mapping exists, a conflict is a one-line note, and a review is a scan, not a resurrection of the whole takeoff.
That is exactly the discipline we build for estimators who are tired of finding the discrepancy at bid time instead of before it. A structured takeoff where the schedule, the sections, and the risk register connect is what an estimating process with compliance included looks like — and whether the points pricing fits how you bid is a question the number answers quickly.
The schedule tells you what you are selling. The section tells you whether it fits. Trust the schedule for the count, the section for the condition, and never let a disagreement disappear silently into your takeoff.